Kitchen Demolition and Rough In
The Loudest Week, and the One That Sets the Pace
Demolition is the shortest stage of a kitchen remodel and the one with the most influence on everything after it. It is where hidden conditions show up, and rough in is where the choices you made on paper become wires and pipes in the wall. Thelanguagebear treats these two stages as one service, because a clean demolition and a well planned rough in are what let the rest of the schedule hold.
Before Anything Comes Out
The first morning is spent protecting the house, not tearing out the kitchen. Floors along the path to the door are covered. A plastic dust wall with a zip door separates the kitchen from the rest of the home. HVAC returns in the work area are sealed so fine dust does not circulate through the ducts. Water is shut off and capped, and circuits feeding the kitchen are turned off and verified dead before anyone touches them.
Demolition Itself
On most kitchens, removing upper and lower cabinets, countertops, backsplash, soffits and old flooring takes two to four days. It goes faster when we are not saving anything and slower when you want cabinets kept for a garage or a laundry room, since those have to come off the wall intact.
What We Look For Once the Walls Are Open
- Water damage. Rot under the sink base, stained subfloor behind the dishwasher or mold on the back of drywall. These get fixed now, not covered.
- Older wiring. Two prong circuits, cloth insulated wire or overloaded shared circuits are common in 1950s and 1960s homes in Olde Carlsbad and near the Village.
- Old drain and supply lines. Galvanized steel supply pipe and aging cast iron drains often need replacing back to a sensible connection point.
- Framing surprises. Previous remodels sometimes cut studs or joists to fit a duct or a pipe. Those are repaired before cabinets go on.
When we find something, you get photos and a plain explanation of what it adds in days and dollars before we proceed.
Rough Plumbing
Keeping the sink where it is saves time and money. Moving it a few feet along the same wall is usually straightforward. Moving it to an island means new drain routing with correct slope, venting that meets code and sometimes cutting into the slab or working in the crawl space. Rough plumbing also covers the dishwasher supply and drain, a refrigerator water line if needed, and gas line changes if the range is moving.
Rough Electrical
Current kitchens carry more load than the ones most Carlsbad homes were built with. Rough electrical typically includes dedicated circuits for the dishwasher, disposal, microwave and refrigerator, countertop receptacle circuits with GFCI protection, AFCI protection where required, wiring for under cabinet lighting and pendants, and the hood circuit. If you are switching to induction, we check panel capacity first, because a panel upgrade has its own utility coordination and can add real time.
Ventilation Rough In
A range hood should capture the cooking surface and duct outside rather than recirculate. The duct path is decided now: through an exterior wall, up through an attic, or through a soffit. Large hoods above a certain airflow can trigger make up air requirements. In planned communities, an exterior wall cap may also need HOA approval, which we request early.
The Rough Inspection
Once rough plumbing, electrical and any framing work are complete, the City of Carlsbad inspects before insulation and drywall. Nothing gets closed until that passes. We book it as soon as rough in is on track, and the date goes on your schedule so you know when the walls start going back up.
Call Before You Start Tearing Out
If you are planning a kitchen and want to know what demolition and rough in will involve in your house, call (442) 419-3532.